A junior exploration company proposes mechanized drilling in McVittie Township, Timiskaming District, about 2.6 kilometres northeast of Larder Lake and about 26 kilometres east of Kirkland Lake.
Waiting on a decisionstatus
39 dayswaiting since it was posted on 21 Sep 2026
When it is likely to be decided
The model puts an 8 in 10 chance on a decision between 5 Nov 2026 and 16 Jan 2028 (our 80% credible interval, shortened elsewhere to the 80% range).
30 Oct 2026Nov 2026Jan 2027Apr 2027Oct 2027
Middle half of the chances (50%)80% range
Forecast made 30 October 2026. Dates are spaced so that the next few weeks and the next few years both fit: the distance from the forecast date grows with the square root of the days.
How it ends
Issued
84%
Refused or withdrawn
14%
Still undecided at the furthest date we look ahead
3%
Key dates
A 1 in 10 chance it is decided by5 Nov 2026
Even odds it is decided by9 Dec 2026
A 9 in 10 chance it is decided by16 Jan 2028
Chance it is decided within 3 months, by 29 Jan 202768%
Chance it is decided within 6 months, by 30 Apr 202778%
Chance it is put on hold before a decision19%
What pushes it earlier or later
The named factors that move the middle date most for this application, in days, compared with an application that is typical on that factor: + means later, − means earlier. They are the largest pieces, not the whole account.
EarlierLater
Heavy drilling planned (drills over 150 kilograms)−26 days
How many decisions the ministry office made in the past six months+20 days
The plan includes drilling+10 days
Applied in 2023 or later+7 days
Outside the Treaty 9 area−4 days
Size of the application+3 days
Applications waiting at the same ministry office−2 days
Public comments received (count published with the decision)+2 days
Holds placed on nearby applications in the past year+1 day
The applicant’s earlier permits+1 day
Some factors about how the ministry handles the file are used but not shown here.
Not yet counted, because the model does not measure them yet: Indigenous nations affected; an impact and benefit agreement; an Indigenous-led assessment; a contested duty to consult; referral to the Minister.
How the forecast has moved
Forecasts for this application side by side. Across: the Friday each was made. Up: the date of the decision. The wider a shape at a date, the likelier a decision then; the dark mark is that week's middle date, and the newest is shaded darker.
Showing 3 of 6 Friday forecasts: the first, the latest, and the weeks it changed, when something happened to the application or the forecast moved more than its usual weekly wobble.
Questions already settled
None of the questions we have asked about this application has been settled yet. The first to settle is whether it is decided by 29 Jan 2027.
The application so far
9 Sep 202630 Oct 2026
Open for public commentUnder review
9 Sep 2026Application submitted to the ministry
12 days later
21 Sep 2026Posted to the registry and opened for public comment
4 weeks later
21 Oct 2026Public comment closed
9 days later
30 Oct 2026Forecast made; still waiting
Dates are the ministry's own. Hover over or tap the strip for the dates and how long each stage took.
Where it is
The registry's own map places this application about 73 kilometres from the mining claims it lists. We cannot tell which place is right, so we show no map.
What the application asks for
Activities
Mechanized drilling (drills over 150 kilograms)
Surroundings
Workload at the ministry office handling it
4 applications waiting; it decided 3 in the past six months
Applicant
A junior exploration company
The applicant’s earlier exploration permits
None before this one