Weekly briefing
Kestrel Bulletin
See what happened last week and what to expect this week from mining regulators. Every week we provide insights on topical issues, publish changes to the permit families we are monitoring, and update our calibration record.
This week’s forecasts
6 files entered coverage on Friday 23 October 2026
153 Ontario exploration permits are waiting on a decision in all. The ones below are those first forecast this week; the others carry ranges published in earlier weeks, and each is graded against its own first range. Every range is an 80% credible interval: the model puts an eight-in-ten chance on the decision being posted to the register between the earliest and latest dates shown. The middle date is the one the model thinks the decision is as likely to come before as after.
| Permit | Registry clock | Applied | Range from 23 Oct 2026 | Earliest | Middle | Latest |
|---|---|---|---|---|---|---|
| 026-1073 | Running | 16 Oct 2026 | 28 Nov 2026 | 6 Jan 2027 | 14 Sep 2031 | |
| 026-1074 | Running | 16 Oct 2026 | 29 Nov 2026 | 6 Jan 2027 | 15 Aug 2030 | |
| 026-1091 | Running | 21 Oct 2026 | 2 Dec 2026 | 9 Jan 2027 | 7 Dec 2029 | |
| 026-1079 | Running | 19 Oct 2026 | 2 Dec 2026 | 12 Jan 2027 | 29 Mar 2029 | |
| 026-1104 | Running | 22 Oct 2026 | 4 Dec 2026 | 16 Jan 2027 | 18 Jan 2030 | |
| 026-1103 | Running | 22 Oct 2026 | 6 Dec 2026 | 12 Feb 2027 | 21 Feb 2033 |
The permit number links to the file’s notice on the public register. Running means the registry’s clock is running on the file; stopped means the registry has put it on hold. A held file is one the registry has stopped the clock on. In this permit type that is almost always consultation with an Indigenous nation. Kestrel forecasts the timing consequence of a hold and says nothing about the adequacy or the course of any consultation. The bars share one scale, drawn as a square root of days so a short range and a range of years both stay readable.
Counts are as Kestrel observed them on Friday 23 October 2026, compared with the Friday before. A file on hold is one the registry has stopped the clock on, almost always to consult an Indigenous nation; it is counted apart because its timing differs. Plans that never reach the registry are not counted. The two waiting cards do not add up to the 153 applications waiting on a decision at the top of the page, because the forecasts also cover files still in their public comment period.
Decisions that landed last week
| Permit | Outcome | Decided | Range first published | Result |
|---|---|---|---|---|
| 026-0888 | Approved | 16 Oct 2026 | 11 Oct 2026 to 10 Aug 2032 | Inside |
| 026-0778 | Approved | 21 Oct 2026 | 4 Sep 2026 to 27 Aug 2032 | Inside |
| 026-0918 | Approved | 22 Oct 2026 | 16 Oct 2026 to 9 Jan 2029 | Inside |
| 026-0929 | Approved | 22 Oct 2026 | 15 Oct 2026 to 17 Jan 2027 | Inside |
Each is graded against the first range published for it. The full list is on the calibration record.
Holds placed or lifted
No hold was placed or lifted between 17 Oct 2026 and 23 Oct 2026.
Special topics
No special topic this week.