An individual proposes mechanized drilling, mechanized stripping, pitting and trenching of bedrock, and line cutting on 12 mining claims covering 5,182 hectares in Pinard Township, Cochrane District, about 4 kilometres northeast of Abitibi Canyon and about 69 kilometres north of Smooth Rock Falls.
Waiting on a decisionstatus
39 dayswaiting since it was posted on 21 Sep 2026
When it is likely to be decided
The model puts an 8 in 10 chance on a decision between 1 Nov 2026 and 4 Dec 2026 (our 80% credible interval, shortened elsewhere to the 80% range).
30 Oct 2026Nov 2026Nov 2026
Middle half of the chances (50%)80% range
Forecast made 30 October 2026. Dates are spaced so that the next few weeks and the next few years both fit: the distance from the forecast date grows with the square root of the days.
How it ends
Issued
99%
Refused or withdrawn
1%
Still undecided at the furthest date we look ahead
under 1%
Key dates
A 1 in 10 chance it is decided by1 Nov 2026
Even odds it is decided by8 Nov 2026
A 9 in 10 chance it is decided by4 Dec 2026
Chance it is decided within 3 months, by 29 Jan 202796%
Chance it is decided within 6 months, by 30 Apr 202798%
Chance it is put on hold before a decision4%
What pushes it earlier or later
The named factors that move the middle date most for this application, in days, compared with an application that is typical on that factor: + means later, − means earlier. They are the largest pieces, not the whole account.
EarlierLater
Heavy drilling planned (drills over 150 kilograms)−3 days
The plan includes drilling+2 days
How many decisions the ministry office made in the past six months+1 day
Applied in 2023 or later+1 day
Some factors about how the ministry handles the file are used but not shown here.
Not yet counted, because the model does not measure them yet: Indigenous nations affected; an impact and benefit agreement; an Indigenous-led assessment; a contested duty to consult; referral to the Minister.
How the forecast has moved
Forecasts for this application side by side. Across: the Friday each was made. Up: the date of the decision. The wider a shape at a date, the likelier a decision then; the dark mark is that week's middle date, and the newest is shaded darker.
Showing 3 of 6 Friday forecasts: the first, the latest, and the weeks it changed, when something happened to the application or the forecast moved more than its usual weekly wobble.
Questions already settled
None of the questions we have asked about this application has been settled yet. The first to settle is whether it is decided by 29 Jan 2027.
The application so far
11 Sep 202630 Oct 2026
Open for public commentUnder review
11 Sep 2026Application submitted to the ministry
10 days later
21 Sep 2026Posted to the registry and opened for public comment
4 weeks later
21 Oct 2026Public comment closed
9 days later
30 Oct 2026Forecast made; still waiting
Dates are the ministry's own. Hover over or tap the strip for the dates and how long each stage took.
Where it is
5 km
Where in Ontario
The outlined area is the mining claims the application covers, 5,182 hectares in all.
What the application asks for
Activities
Line cutting (wider than 1.5 metres)
Mechanized stripping (over 100 square metres within a 200 metre radius)
Pitting and trenching of bedrock (over 3 cubic metres within a 200 metre radius)
Mechanized drilling (drills over 150 kilograms)
Mining claims covered
12
Area of those claims
5,182 hectares
Surroundings
Holds within 50 kilometres in the past year
none held for consultation with an Indigenous nation; none put on a temporary hold
Other exploration plans in circulation within 50 kilometres
2
Workload at the ministry office handling it
9 applications waiting; it decided 18 in the past six months