A junior exploration company proposes mechanized drilling on 42 mining claims covering 987 hectares in Blakelock Township, Cochrane District, about 62 kilometres north of Kirke and about 77 kilometres northeast of Cochrane.
The model puts an 8 in 10 chance on a decision between 31 Oct 2026 and 28 May 2027 (our 80% credible interval, shortened elsewhere to the 80% range).
30 Oct 2026Nov 2026Dec 2026Apr 2027
Middle half of the chances (50%)80% range
Forecast made 30 October 2026. Dates are spaced so that the next few weeks and the next few years both fit: the distance from the forecast date grows with the square root of the days.
How it ends
Issued
96%
Refused or withdrawn
3%
Still undecided at the furthest date we look ahead
1%
Key dates
A 1 in 10 chance it is decided by31 Oct 2026
Even odds it is decided by18 Nov 2026
A 9 in 10 chance it is decided by28 May 2027
Chance it is decided within 3 months, by 29 Jan 202781%
Chance it is decided within 6 months, by 30 Apr 202788%
Chance it is put on hold before a decision12%
What pushes it earlier or later
The named factors that move the middle date most for this application, in days, compared with an application that is typical on that factor: + means later, − means earlier. They are the largest pieces, not the whole account.
EarlierLater
Heavy drilling planned (drills over 150 kilograms)−16 days
The plan includes drilling+7 days
How many decisions the ministry office made in the past six months+4 days
Applied in 2023 or later+4 days
Outside the Treaty 9 area−2 days
Size of the application (42 mining claims)−1 day
Public comments received (count published with the decision)+1 day
Holds placed on nearby applications in the past year+1 day
Applications waiting at the same ministry office−1 day
Some factors about how the ministry handles the file are used but not shown here.
Not yet counted, because the model does not measure them yet: Indigenous nations affected; an impact and benefit agreement; an Indigenous-led assessment; a contested duty to consult; referral to the Minister.
How the forecast has moved
Forecasts for this application side by side. Across: the Friday each was made. Up: the date of the decision. The wider a shape at a date, the likelier a decision then; the dark mark is that week's middle date, and the newest is shaded darker.
Oct 2026Jan 2027Apr 2027Jul 2027
11 SepFirst forecast16 OctPublic comment closed30 OctLatest; forecast moved
Showing 3 of 8 Friday forecasts: the first, the latest, and the weeks it changed, when something happened to the application or the forecast moved more than its usual weekly wobble.
Questions already settled
None of the questions we have asked about this application has been settled yet. The first to settle is whether it is decided by 29 Jan 2027.
The application so far
27 Aug 202630 Oct 2026
Open for public commentUnder review
27 Aug 2026Application submitted to the ministry
13 days later
9 Sep 2026Posted to the registry and opened for public comment
4 weeks later
9 Oct 2026Public comment closed
3 weeks later
30 Oct 2026Forecast made; still waiting
Dates are the ministry's own. Hover over or tap the strip for the dates and how long each stage took.
Where it is
2 km
Where in Ontario
The outlined area is the mining claims the application covers, 987 hectares in all.
What the application asks for
Activities
Mechanized drilling (drills over 150 kilograms)
Mining claims covered
42
Area of those claims
987 hectares
Surroundings
Holds within 50 kilometres in the past year
none held for consultation with an Indigenous nation; none put on a temporary hold
Other exploration plans in circulation within 50 kilometres
2
Workload at the ministry office handling it
7 applications waiting; it decided 21 in the past six months
Applicant
A junior exploration company
The applicant’s earlier exploration permits
None before this one
Published Mondays, noon Toronto timeKestrel EconomicsBULLETIN