When it is likely to be decided
The model puts an 8 in 10 chance on a decision between 5 Nov 2026 and 14 Jun 2028 (our 80% credible interval, shortened elsewhere to the 80% range).
30 Oct 2026Nov 2026Apr 2027Oct 2027Oct 2028
Middle half of the chances (50%) 80% range
Forecast made 30 October 2026. Dates are spaced so that the next few weeks and the next few years both fit: the distance from the forecast date grows with the square root of the days.
What pushes it earlier or later
The named factors that move the middle date most for this application, in days, compared with an application that is typical on that factor: + means later, − means earlier. They are the largest pieces, not the whole account.
EarlierLater
Heavy drilling planned (drills over 150 kilograms) −40 days
The plan includes drilling +15 days
How many decisions the ministry office made in the past six months +13 days
Applied in 2023 or later +11 days
Outside the Treaty 9 area −7 days
Holds placed on nearby applications in the past year −3 days
Size of the application (41 mining claims) −3 days
Public comments received (count published with the decision) +2 days
Applications waiting at the same ministry office −1 day
The applicant’s earlier permits +1 day
Some factors about how the ministry handles the file are used but not shown here.
Not yet counted, because the model does not measure them yet: Indigenous nations affected; an impact and benefit agreement; an Indigenous-led assessment; a contested duty to consult; referral to the Minister.
How the forecast has moved
Forecasts for this application side by side. Across: the Friday each was made. Up: the date of the decision. The wider a shape at a date, the likelier a decision then; the dark mark is that week's middle date, and the newest is shaded darker.
14 AugFirst forecast28 AugForecast moved4 SepForecast moved18 SepForecast moved25 SepApplication submitted to the ministry9 OctForecast moved23 OctForecast moved30 OctLatest; forecast moved
Showing 8 of 12 Friday forecasts: the first, the latest, and the weeks it changed, when something happened to the application or the forecast moved more than its usual weekly wobble. At most 8 are shown; when there are more, the weeks with the biggest moves are kept.
The application so far
4 Jun 202630 Oct 2026
Open for public comment
Under review
- 4 Jun 2026 Application submitted to the ministry
- 5 weeks later
- 7 Jul 2026 Posted to the registry and opened for public comment
- 4 weeks later
- 6 Aug 2026 Public comment closed
- 3 months later
- 30 Oct 2026 Forecast made; still waiting
Dates are the ministry's own. Hover over or tap the strip for the dates and how long each stage took.