This week / Ontario exploration permit

026-0601

An individual proposes mechanized drilling, mechanized stripping, pitting and trenching of bedrock, and line cutting on 14 mining claims covering 303 hectares in Skead Township, Timiskaming District, about 15 kilometres south of Larder Lake and about 19 kilometres northeast of Englehart.

Waiting on a decisionstatus
148 dayswaiting since it was posted on 4 Jun 2026

When it is likely to be decided

The model puts an 8 in 10 chance on a decision between 11 Nov 2026 and 17 Jun 2028 (our 80% credible interval, shortened elsewhere to the 80% range).

30 Oct 2026Nov 2026Apr 2027Oct 2027Oct 2028
Middle half of the chances (50%) 80% range

Forecast made 30 October 2026. Dates are spaced so that the next few weeks and the next few years both fit: the distance from the forecast date grows with the square root of the days.

How it ends

Issued
91%
Refused or withdrawn
5%
Still undecided at the furthest date we look ahead
4%

Key dates

  • A 1 in 10 chance it is decided by11 Nov 2026
  • Even odds it is decided by14 Feb 2027
  • A 9 in 10 chance it is decided by17 Jun 2028
  • Chance it is decided within 3 months, by 29 Jan 202744%
  • Chance it is decided within 6 months, by 30 Apr 202767%
  • Chance it is put on hold before a decision33%

What pushes it earlier or later

The named factors that move the middle date most for this application, in days, compared with an application that is typical on that factor: + means later, − means earlier. They are the largest pieces, not the whole account.

EarlierLater
Heavy drilling planned (drills over 150 kilograms) −37 days
The plan includes drilling +24 days
Applied in 2023 or later +11 days
Holds placed on nearby applications in the past year −10 days
How many decisions the ministry office made in the past six months +9 days
Outside the Treaty 9 area −6 days
Public comments received (count published with the decision) +2 days
Applications waiting at the same ministry office −2 days
The applicant’s earlier permits +1 day
Size of the application (14 mining claims) −1 day

Some factors about how the ministry handles the file are used but not shown here.

Not yet counted, because the model does not measure them yet: Indigenous nations affected; an impact and benefit agreement; an Indigenous-led assessment; a contested duty to consult; referral to the Minister.

How the forecast has moved

Forecasts for this application side by side. Across: the Friday each was made. Up: the date of the decision. The wider a shape at a date, the likelier a decision then; the dark mark is that week's middle date, and the newest is shaded darker.

Jan 2027Jul 2027Jan 2028
14 AugFirst forecast28 AugForecast moved11 SepForecast moved25 SepForecast moved9 OctForecast moved23 OctForecast moved30 OctLatest; forecast moved

Showing 7 of 12 Friday forecasts: the first, the latest, and the weeks it changed, when something happened to the application or the forecast moved more than its usual weekly wobble.

Questions already settled

  • Not as we said

    On 24 July 2026 we gave a 79% chance that it would be decided by 23 October 2026. It wasn’t.

    Made before the calibration record began on 14 August 2026, so it is not counted in the record.

  • Not as we said

    On 31 July 2026 we gave a 71% chance that it would be decided by 30 October 2026. It wasn’t.

    Made before the calibration record began on 14 August 2026, so it is not counted in the record.

The application so far

28 May 202630 Oct 2026
Open for public comment Under review
  1. 28 May 2026 Application submitted to the ministry
  2. 7 days later
  3. 4 Jun 2026 Posted to the registry and opened for public comment
  4. 4 weeks later
  5. 4 Jul 2026 Public comment closed
  6. 4 months later
  7. 30 Oct 2026 Forecast made; still waiting

Dates are the ministry's own. Hover over or tap the strip for the dates and how long each stage took.

Where it is

0.5 km
Where in Ontario

The outlined area is the mining claims the application covers, 303 hectares in all.

What the application asks for

Activities
  • Line cutting (wider than 1.5 metres)
  • Mechanized stripping (over 100 square metres within a 200 metre radius)
  • Pitting and trenching of bedrock (over 3 cubic metres within a 200 metre radius)
  • Mechanized drilling (drills over 150 kilograms)
Mining claims covered
14
Area of those claims
303 hectares

Surroundings

Holds within 50 kilometres in the past year
4 applications held for consultation with an Indigenous nation; none put on a temporary hold
Other exploration plans in circulation within 50 kilometres
9
Workload at the ministry office handling it
5 applications waiting; it decided 23 in the past six months
Applicant
An individual
The applicant’s earlier exploration permits
None before this one