This week / Ontario exploration permit

019-8734

A mid-sized mining company proposes mechanized drilling on 15 mining claims covering 296 hectares in Hewitt Lake Area, Kenora District, about 14 kilometres southeast of North Spirit Lake and about 79 kilometres south of Sandy Lake.

On holdwaiting on consultation with an Indigenous nation
889 dayswaiting since it was posted on 24 May 2024
70% chancestill waiting on 27 May 2030

When it is likely to be decided

More likely than not, this application will still be waiting on 27 May 2030, the furthest date the model looks ahead. If it is decided before then, the curve shows when.

70%
30 Oct 2026Dec 2026Oct 2027Oct 202827 May 2030
Middle half of the chances (50%) 80% range Still waiting at the furthest date (bar height = its share)
70% chance still undecided on 27 May 2030, the furthest date the model looks ahead

The model looks ahead 3.6 years from the forecast date, to 27 May 2030. It does not try to say when an application still waiting after that will be decided, so every such case is counted together at that date. The bar on the right is that share: the chance this application is still waiting then. It is not a date we expect a decision on. The curve to its left shares out the rest, 30%, over the dates before it.

Forecast made 30 October 2026. Dates are spaced so that the next few weeks and the next few years both fit: the distance from the forecast date grows with the square root of the days.

How it ends

Issued
17%
Refused or withdrawn
13%
Still undecided at the furthest date we look ahead
70%

Key dates

  • A 1 in 10 chance it is decided by26 Sep 2027
  • A 70% chance it is still waiting on27 May 2030
  • Chance it is decided within 3 months, by 29 Jan 20273%
  • Chance it is decided within 6 months, by 30 Apr 20276%
  • Already on hold (waiting on consultation with an Indigenous nation) since 26 Aug 2024On hold

What pushes it earlier or later

The named factors that move the middle date most for this application, in days, compared with an application that is typical on that factor: + means later, − means earlier. They are the largest pieces, not the whole account.

EarlierLater
The plan includes drilling +45 days
Applied in 2023 or later +33 days
The applicant’s earlier permits −15 days
Applications waiting at the same ministry office +14 days
How many decisions the ministry office made in the past six months −5 days
Outside the Treaty 9 area −5 days
Heavy drilling planned (drills over 150 kilograms) +2 days
Holds placed on nearby applications in the past year −2 days
Public comments received (count published with the decision) +2 days
Size of the application (15 mining claims) +1 day

Not yet counted, because the model does not measure them yet: Indigenous nations affected; an impact and benefit agreement; an Indigenous-led assessment; a contested duty to consult; referral to the Minister.

How the forecast has moved

Forecasts for this application side by side. Across: the Friday each was made. Up: the date of the decision. The wider a shape at a date, the likelier a decision then; the dark mark is that week's middle date, and the newest is shaded darker. A percentage at the top of a column is the chance of still waiting at the furthest date that forecast looked ahead; each shape below it is drawn to its own width, so it shows when a decision is likeliest if one comes.

2027202820292030203154%66%71%70%
14 AugFirst forecast28 AugForecast moved9 OctForecast moved30 OctLatest

Showing 4 of 12 Friday forecasts: the first, the latest, and the weeks it changed, when something happened to the application or the forecast moved more than its usual weekly wobble.

Questions already settled

  • As we said

    On 24 July 2026 we gave a 94% chance that it would not be decided by 23 October 2026. It wasn’t.

    Made before the calibration record began on 14 August 2026, so it is not counted in the record.

  • As we said

    On 31 July 2026 we gave a 94% chance that it would not be decided by 30 October 2026. It wasn’t.

    Made before the calibration record began on 14 August 2026, so it is not counted in the record.

The application so far

29 Apr 202430 Oct 2026
Open for public comment Under review On hold
  1. 29 Apr 2024 Application submitted to the ministry
  2. 4 weeks later
  3. 24 May 2024 Posted to the registry and opened for public comment
  4. 4 weeks later
  5. 23 Jun 2024 Public comment closed
  6. 9 weeks later
  7. 26 Aug 2024 Put on hold to consult an Indigenous nation
  8. Same day
  9. 26 Aug 2024 Put on hold: a temporary hold
  10. 2.2 years later
  11. 30 Oct 2026 Forecast made; still waiting

Dates are the ministry's own. Hover over or tap the strip for the dates and how long each stage took.

Where it is

1 km
Where in Ontario

The outlined area is the mining claims the application covers, 296 hectares in all.

What the application asks for

Activities
  • Mechanized drilling (drills over 150 kilograms)
Mining claims covered
15
Area of those claims
296 hectares

Surroundings

Holds within 50 kilometres in the past year
none held for consultation with an Indigenous nation; none put on a temporary hold
Other exploration plans in circulation within 50 kilometres
1
Workload at the ministry office handling it
108 applications waiting; it decided 65 in the past six months