Kestrel Economics · Bulletin Beta

This week / Ontario exploration permit

019-7112

A junior exploration company proposes mechanized stripping and line cutting on 2 mining claims covering 758 hectares in Thunder Bay District, about 15 kilometres south of Hillsport and about 32 kilometres northeast of Manitouwadge.

On holdwaiting on consultation with an Indigenous nation
1,255 dayswaiting since it was posted on 24 May 2023
51% chancestill waiting on 16 Apr 2027

When it is likely to be decided

More likely than not, this application will still be waiting on 16 April 2027, the furthest date the model looks ahead. If it is decided before then, the curve shows when.

51%
30 Oct 2026Nov 2026Dec 202616 Apr 2027
Middle half of the chances (50%) 80% range Still waiting at the furthest date (bar height = its share)
51% chance still undecided on 16 April 2027, the furthest date the model looks ahead

The model looks ahead 6 months from the forecast date, to 16 April 2027. It does not try to say when an application still waiting after that will be decided, so every such case is counted together at that date. The bar on the right is that share: the chance this application is still waiting then. It is not a date we expect a decision on. The curve to its left shares out the rest, 50%, over the dates before it.

Forecast made 30 October 2026. Dates are spaced so that the next few weeks and the next few years both fit: the distance from the forecast date grows with the square root of the days.

How it ends

Issued
32%
Refused or withdrawn
17%
Still undecided at the furthest date we look ahead
51%

Key dates

  • A 1 in 10 chance it is decided by21 Nov 2026
  • A 51% chance it is still waiting on16 Apr 2027
  • Chance it is decided within 3 months, by 29 Jan 202731%
  • Chance it is decided within 6 months, by 30 Apr 202750%
  • Already on hold (waiting on consultation with an Indigenous nation) since 16 Apr 2025On hold

What pushes it earlier or later

The named factors that move the middle date most for this application, in days, compared with an application that is typical on that factor: + means later, − means earlier. They are the largest pieces, not the whole account.

EarlierLater
Applied in 2023 or later −6 days
Applications waiting at the same ministry office +2 days
The applicant’s earlier permits +1 day
Outside the Treaty 9 area −1 day

Not yet counted, because the model does not measure them yet: Indigenous nations affected; an impact and benefit agreement; an Indigenous-led assessment; a contested duty to consult; referral to the Minister.

How the forecast has moved

Forecasts for this application side by side. Across: the Friday each was made. Up: the date of the decision. The wider a shape at a date, the likelier a decision then; the dark mark is that week's middle date, and the newest is shaded darker. A percentage at the top of a column is the chance of still waiting at the furthest date that forecast looked ahead; each shape below it is drawn to its own width, so it shows when a decision is likeliest if one comes.

Oct 2026Jan 2027Apr 202742%44%48%47%48%55%49%51%
14 AugFirst forecast21 AugForecast moved11 SepForecast moved25 SepForecast moved9 OctForecast moved16 OctForecast moved23 OctForecast moved30 OctLatest

Showing 8 of 12 Friday forecasts: the first, the latest, and the weeks it changed, when something happened to the application or the forecast moved more than its usual weekly wobble. At most 8 are shown; when there are more, the weeks with the biggest moves are kept.

Questions already settled

  • As we said

    On 24 July 2026 we gave a 67% chance that it would not be decided by 23 October 2026. It wasn’t.

    Made before the calibration record began on 14 August 2026, so it is not counted in the record.

  • As we said

    On 31 July 2026 we gave a 65% chance that it would not be decided by 30 October 2026. It wasn’t.

    Made before the calibration record began on 14 August 2026, so it is not counted in the record.

The application so far

24 May 202330 Oct 2026
Open for public comment Under review On hold
  1. 24 May 2023 Posted to the registry and opened for public comment
  2. 4 weeks later
  3. 23 Jun 2023 Public comment closed
  4. 22 months later
  5. 16 Apr 2025 Put on hold to consult an Indigenous nation
  6. 18 months later
  7. 30 Oct 2026 Forecast made; still waiting

Dates are the ministry's own. Hover over or tap the strip for the dates and how long each stage took.

Where it is

1 km
Where in Ontario

The outlined area is the mining claims the application covers, 758 hectares in all.

What the application asks for

Activities
  • Line cutting (wider than 1.5 metres)
  • Mechanized stripping (over 100 square metres within a 200 metre radius)
Mining claims covered
2
Area of those claims
758 hectares

Surroundings

Holds within 50 kilometres in the past year
none held for consultation with an Indigenous nation; 2 applications put on a temporary hold
Other exploration plans in circulation within 50 kilometres
4
Workload at the ministry office handling it
108 applications waiting; it decided 40 in the past six months
Applicant
A junior exploration company
The applicant’s earlier exploration permits
None before this one
Published Mondays, noon Toronto time Kestrel EconomicsBULLETIN